Max Goncharov and David Toback
Texas A&M University
Version 1.2 (7/14/03)
This note describes the installation and the checkout of the PEM portion of the EMTiming system. The highest priority is the safety of the already working plug calorimeter so all installation work on the detector itself will be done by under the instruction and supervision of Dervin. This document is designed to put into writing a chronologically detailed and pictorial description of the instructions and what are the places to be particularly careful of. It follows closely the installation of the 3 wedges that were successfully done in January 2003. We have detailed the set of checks the TAMU group will perform before and after every day of installation to test if the installation adversely affects any other detector system; allowing any problems to be caught and fixed in real time. Section 1 describes the before and after testing, Section 2 describes the installation itself and Section 3 shows more pictures of the parts which are the most sensitive to being disturbed during the installation itself.
(Work done by TAMU group)
Texas
A&M People: Slava Krutelyov (630-218-8916,
x2120), Sung-Won Lee (x6647), Max Goncharov (630-476-0774, x2120); all have ACE
training
System
Experts: in event of a problem detected the experts
for the affected system will be called immediately. They are:
|
Light Box (Plug PMTs,
High Voltage connectors and cables) |
Willis Sakumoto, Howard Budd, Mike Lindgren |
|
Plug Front End
Electronics |
Mark Mattson, Robin Erbacher |
|
PES, PPR |
Karen Byrum, Mike Lindgren, Steve Kuhlmann |
Upon detection of the problem we stop the installation until the experts for the affected system allow the installation to proceed.
While working on the PEM the installers will come close physically to several PEM parts that are sensitive to being not treated carefully. One needs to check the state of the system before and after installation. There are two points in the PEM that might be affected: PEM light box[1] and PEM relay rack. We will perform the standard calibrations to check that the installation did not affect other parts of the system. To perform calibrations we need a running DAQ system. It is expected that the system will be available with the exception of 3 days scheduled (from Frank Chlebana) for the system upgrade. We will do the following (summarized in Table 1):
The calibration is standard and can be performed by any ACE on a regular basis; we have 3 persons with ACE training to run them (Sung-Won Lee, Slava Krutelov, and Max Goncharov). The test takes ~50 min. We are going to perform the calibrations at the beginning and at the end of every day of the installation. There is a standard way in DBANA to determine if there are changes in the system. If any changes in any of the systems occur an expert will be called and the installation will be stopped and not resumed unless there is time to evaluate why the failure occurred, so it won’t happen again. The installation will not be resumed without the approval of SPLs/operations. The installation of a single wedge (Section 2) takes much more time than the full set of calibrations, so we have enough time to catch failures in real time.
|
Components: |
Time |
||||||
|
Plug Laser |
CHA PMT CEM PMT |
High Voltage |
Readout |
~30 min |
|
||
|
ShowerMax |
Crate |
|
|
Readout |
~15 min |
|
|
|
Cosmic Rays |
Strips & Wires |
PPR |
Cables |
(Readout) |
~8 hours (overnight) |
|
|
Table 1: Calibration – System hardware map. Here “Cables” means the cables that connect the Light Box with the boards in the readout crates. By Readout we mean the cables from the crate to upstairs (Crate, ADMEM, long cables).
Work done by:
Jamie Grado, Lew Morris (FNAL)
Fabio Happacher, Andrea Sansoni, Giovanni Bisogni, Mario Anelli (Frascati)
Only people approved and trained by Dervin will do the installation. Each crew consists of 2 persons under his supervision, and they are to work with safety and carefulness (rather than speed) being their highest priority. In this section we detail the steps to install each wedge as well as point out the potential danger spots. In January 2003 it took approximately one hour per harness. Section 3 provides more pictures about some of the more sensitive parts that require extra attention during installation.
The general layout of the plug detector is shown on Figure 1. All harnesses connect the Plug Light Box dynode outputs with the TB/ASD that are installed in the middle crate of the Relay Rack. Each harness has 2 AMP connectors for the Light Box side and lemo connectors for the TB side; see Figure 2.
The installation procedure:
Texas A&M people (Max Goncharov, Sung-Won Lee, Slava Krutelyov) after training from Dervin will assist with plugging the AMP connectors into the Light Box. When the installation moves to the other side of the Plug detector (North-South), a person from Texas A&M group will check if all AMP connector pins are functioning[2]. After that the harness LEMO connectors can be hooked up to the Transition Board and the cables can be dressed at both ends. The dressing is expected to take 1 person day per side.

Figure 1
Plug detector layout. All Harnesses go into the central crate of the relay rack. Each black line indicates two harnesses and which Relay Rack/Crate they go to, but not their pass through the penetrations.

Figure 2
Full view of the PEM harness.

Figure 3
Insertion Hole in the
Plug. This shows three PEM harnesses on their path from the Relay Rack to the
cable tray and Light Box.

Figure 4
This picture shows the Plug Light Box and the plug harness already installed but not connected (See next Figure). The most sensitive parts are the other AMP connectors that should not be bumped. There are 2 PEM harnesses per box, each harness has two AMP connectors. Right now PMT dynode outputs are terminated into 50 Ohm AMP terminator.

Figure 5
The Plug Light Box: one of the old 50 Ohm AMP terminators has been removed and the PEM harness AMP connector is ready to be plugged into the Light Box. The pins inside AMP connectors are very delicate and can be easily damaged or bent and not make proper connection. Plugging them incorrectly is the most sensitive part of the installation.

Figure 6
Three PEM harnesses plugged into the back of a transition board in the middle crate of the relay rack.